Italy’s Energy Release 2.0 scheme has formally entered its build-out phase, with 22.5 TWh contracted to energy-intensive users and developers now moving to secure the renewable capacity required under 20-year restitution obligations.
Italy’s Energy Release 2.0 mechanism has moved into its operational phase, with GSE (Italy’s public body in charge of renewable auctions) confirming earlier this month that 476 contracts were signed by energy-intensive end users and aggregators by the 31 January 2026 deadline, covering a total allocated volume of 22.5 TWh. The scheme allows large industrial consumers to secure renewable electricity at a fixed price of 65 EUR/MWh in the short term, in exchange for a binding obligation to develop new renewable capacity over time.
According to GSE’s announcement, from February 16 to March 9, 2026, participants may formally delegate the obligation to build new renewable capacity to a producer by signing a so-called “addendum” to the contract through the E-RELEASE portal. This delegation is executed via a tripartite clause signed by GSE, the aggregator or energy-intensive user, and the renewable developer.
Several transactions have already emerged. In late January, aggregator Duferco Energia and developer Gruppo Carlo Maresca agreed to develop around 60 MW of new PV capacity in Italy under the scheme, supplying renewable power at GSE-defined prices to Duferco’s industrial clients. The project is expected to be completed within the GSE deadline of 40 months from signature. Meanwhile, Edison Next signed a 20-year off-site PPA with Acciaierie Venete linked to the scheme, starting with a 6.7 MWp plant and potentially expanding to 50 MWp to meet Energy Release obligations.
On 11 February, Greek energy company Metlen announced it had secured a 2.4 TWh supply contract with Acciaieria Arvedi and planned to commission around 170 MW of new solar capacity in Italy over the next three years. German developer Encavis also announced it had secured addendum contracts totaling 3.7 TWh under the scheme on 19 February, equivalent to more than 16% of the allocated volume, as a delegated third-party with undisclosed energy-intensive companies and aggregators.
As highlighted in a recent Pexapark article, Energy Release’s 2.0 recently updated rules introduced both a competitive allocation for restitution contracts and a claw-back mechanism requiring repayment of any “residual advantage” not effectively returned over the 20-year term. According to a market source, producers leveraged the clause requiring repayment of residual advantage at the end of the term to negotiate higher remuneration, indicating that risk allocation remains a central issue in the scheme’s economics.
The second phase of the scheme is expected to begin before the end of Q1 2026, when GSE will launch a competitive procedure to allocate build obligations for new renewable plants to developers who were not designated through bilateral addenda signed with aggregators or energy-intensive users.
Are you interested in unlocking more market insights?
This article is just one of many expert updates available on Pexapark’s price intelligence platform. Learn more about our BESS price and market intelligence here.
Our market experts frequently share sharp, data-led perspectives on the trends reshaping renewables. To read more, register with Pexapark today for your free month access.