ERCOT’s 2027 demand forecast edged higher in September, signaling that months of data center-driven downward revisions may be easing.

ERCOT’s demand outlook has been red hot on expectations for a massive influx of data centers and other large loads into Texas. But in recent months, those prospects have been sharply tempered as stringent interconnection requirements and stricter oversight threaten to narrow the pipeline of projects that ultimately connect to the grid. A government forecast issued in early September, however, suggests the pullback may finally be leveling off.

The latest ERCOT demand outlook for 2027 was broadly unchanged, signaling that the sharpest erosion stemming from a state-mandated audit and stricter project vetting may now be in the rearview mirror. While the latest forecast remains well below earlier projections, the stabilization suggests near-term load growth may be finding a floor after a string of downward revisions since the beginning of the year. That’s welcome news for renewable energy developers contending with valuations that have retreated from their peaks earlier this year, before the new restrictions took effect.

“Although Texas has paused the connection of new data centers to the grid to facilitate a regulatory audit of proposed data center projects, the West South Central region still accounts for the largest regional share of growth in total electricity sales, totaling nearly 20% of nationwide growth in 2026 and nearly 40% in 2027,” the U.S. Energy Information Administration (EIA) said in its Short-Term Energy Outlook issued 9 September.

According to the report, ERCOT’s net energy for load in 2027 is forecast to reach 526.9 billion kWh, representing a slight upward revision from 526.1 billion kWh projected in August. Still, the latest estimate is nearly 10% below the 585.2 billion kWh forecast for 2027 in January, before the new data center measures were implemented.

The outlook for ERCOT wholesale power prices in 2027 has also held steady, offering another sign that the market may be finding a floor. The September report projects that ERCOT’s benchmark North Hub price will reach 34.30 USD/MWh next year, a 1.6% upward revision from the August forecast. Even so, that’s well below the 44.70 USD/MWh projected in January.

With its industry-friendly climate and abundant energy resources, ERCOT continues to vie with PJM as one of the nation’s leading destinations for data centers. But recent actions by state officials underscore how Texas is seeking to put guardrails around unfettered data center development to shield consumers and communities from rising costs and other impacts.

The brunt of the impact on the demand outlook came in early August, after Texas Gov. Greg Abbott announced an extensive audit of proposed data center projects that halted ERCOT’s new “Batch Zero” interconnection process and subjected projects to additional scrutiny before they could advance. To reflect those actions, the EIA slashed its 2027 Texas electricity demand forecast to 526.1 billion kWh in its August report, marking an 8% cut from the prior forecast. The subsequent upticks in both the demand and price forecasts in September, however, suggest that months of consistent downward revisions may be coming to an end.

Additional constraints on load growth are expected from ERCOT’s “Batch Zero” process itself, which is due to resume after the audit of data center projects concludes in December. While the new system is designed to speed up interconnection for more advanced projects by evaluating them in batches, tougher eligibility requirements are narrowing the pipeline by screening out speculative proposals and delaying less mature developments. Projects that do advance will face greater competition for limited transmission and distribution capacity across the grid.

 