Inertia Procurement Opens New Income Stream for Grid-Forming BESS in Germany

German TSOs have now launched the procurement of inertia services, setting fixed long term price levels that allow BESS assets to monetize inertia as an additional but limited revenue stream.

Back in 2025, German TSOs announced that they would begin compensating BESS assets for the provision of inertia services, a development Pexapark reported on in June 2025. Inertia refers to the power system’s inherent and immediate physical response to imbalances between generation and demand within milliseconds, helping to prevent breaches of frequency stability limits.

The TSOs have now started procuring inertia services and have published the corresponding price levels for the different products. The remuneration for providing inertia services is based on a fixed price over the contract tenor, with tenors ranging from 2 to 10 years that can be chosen by the BESS owner.

Four product categories are available: premium and base (varying by the required availability level), each in positive and negative direction (depending on the direction of inertia response).

Base products require an availability of 30%, while premium products require 90%. For BESS assets, the TSOs foresee participation primarily in the premium product, as batteries are able to guarantee the higher availability. The base products are also accessible to demand side response assets for positive inertia and to wind and solar assets for negative inertia, provided that grid-forming inverters are installed.

Pricing consists of a fixed base component, and an additional component for higher availability of the units. For the premium product, the base price is set at 805 EUR/MWs/y. When availability exceeds 90%, remuneration increases linearly up to 888.5 EUR/MWs/y at 100% availability. Availability is defined as the share of 15-minute intervals during which the contracted inertia capacity is available on an average basis and the asset remains continuously synchronized. In practical terms, this means that a BESS asset can participate in ancillary capacity markets without affecting inertia availability, whereas activation in other markets may reduce the inertia availability.

Another important aspect is the dimensioning of the capacity that can be awarded. Asset owners can define the so-called m-factor, which determines the share of the BESS capacity that receives compensation for inertia. The selection of the m-factor depends on the oversizing of the inverter relative to the BESS capacity, which allows the battery to exceed its nominal capacity limits for short timeframes, as well as on the trade-off between committing capacity to the inertia contract and preserving flexibility for other BESS revenue streams.

How is the available capacity calculated, and how much revenue can this generate for a BESS owner?

By way of example, a 1 MW BESS with an activation period, referred to as the Anlaufzeitkonstante, of 25 seconds and an m-factor of 0.3 would be able to offer the following inertia capacity, defined as Momentanreserve:

0.5 × 0.3 × 25 s × 1 MW = 3.75 MWs

This 3.75 MWs would be remunerated at 805 EUR/MWs/y, resulting in revenues of 3019 EUR/MW/y at an availability of 90%. As a BESS can provide both positive and negative inertia simultaneously, this amount would double to 6038 EUR/MW/y.

While this corresponds to only around 3% of the total annual revenues a 2-h BESS asset could have generated last year1, it nevertheless represents a stable revenue base that does not materially limit other revenue streams, provided that not too much capacity is reserved for inertia.

Prices will to remain at this level for 2026 and 2027, with new price levels scheduled to be published by July 2027 for 2028 and 2029.

The inertia demand is set per TSO zone and for positive as well as negative inertia. The demand is mainly centred around northern Germany, with the highest demands in the TSO areas of TenneT and 50Hertz. The contracts are awarded on a first-come-first served basis, until the demand is met.


Source: Netztransparenz.net.

On the technical side, BESS assets must be equipped with grid forming inverters to provide inertia, which may increase system capex.

The first optimization deal incorporating a grid-forming inverter in Germany tracked by Pexapark in its BESS Deal Tracker involves a 20 MW / 55 MWh BESS developed by Schoenergie and optimized by Enspired and Entelios.

Note: 1 Based on 2 cycles per day, 85% RTE and perfect foresight.

 

Are you interested in unlocking more market insights?

This article is just one of many expert updates available on Pexapark’s price intelligence platform. Learn more about our BESS price and market intelligence here.

Our market experts frequently share sharp, data-led perspectives on the trends reshaping renewables. To read more, register with Pexapark today for your free month access.